Why do so many crews skip checking the anchor torque log on lift plans?
I run a small steel erection crew out of Columbus and I keep running into the same thing on job sites: guys pull a lift plan out of the folder, look at the load chart, and skip right past the anchor and base plate torque section at the bottom. Last month on a 4 story job near Dublin we found 6 anchor bolts under spec on a column that had already been set. The plan said 200 ft-lbs and the log sheet was blank because the ironworker before us never wrote it down. That stuff is not paperwork for paperwork's sake, if those anchors slip the whole moment frame changes behavior and someone gets hurt. I now make my guys initial and date every single bolt in the torque column before we move to the next bay, and it has caught two more problems since. So my ask is, does anyone have a free or cheap torque tracking sheet they like for steel jobs, because mine is just a printed grid and I know there has to be a better way.